Division |
WorkDescription |
Location |
Contract Commencement |
Estimated Completion |
Status |
Jurong Spring |
Repairs And Redecoration Works |
Blk 543 to 549 Jurong West St 42 |
1st Quarter 2019 |
1st Quarter 2021 |
Completed |
Yuhua |
Replacement Of Booster Pumpset With Control Panels |
Blk 209 to 240 Jurong East St 21 |
1st Quarter 2019 |
1st Quarter 2021 |
Completed |
Bukit Batok East |
Repairs And Redecoration Works |
Blk 242 to 253 Bukit Batok East Ave 4/Ave 5 |
1st Quarter 2020 |
3rd Quarter 2021 |
Completed |
Bukit Batok |
Repairs And Redecoration Works |
Blk 101 to 110 Bukit Batok West Ave 6 |
1st Quarter 2021 |
3rd Quarter 2023 |
In Progress |
Bukit Batok |
Repairs And Redecoration Works |
Blk 133 to 139 Bukit Batok West Ave 6 |
1st Quarter 2021 |
4th Quarter 2021 |
Completed |
Jurong Spring |
Repairs And Redecoration Works |
Blk 456 to 461, 517A, 517C to 517F, 518A, 530A Jurong West St 41/St 52 |
2nd Quarter 2020 |
2nd Quarter 2022 |
Completed |
Taman Jurong |
Repairs And Redecoration Works |
Blk 116 to 122 Ho Ching Rd |
2nd Quarter 2020 |
3rd Quarter 2021 |
Completed |
Bukit Batok |
Repairs And Redecoration Works |
Blk 623 to 630, 632 to 634, 636 to 644, 230A Bukit Batok Central/St 21 |
3rd Quarter 2019 |
3rd Quarter 2021 |
Completed |
Bukit Batok East |
Repairs And Redecoration Works |
Blk 290A-G Bukit Batok St 24 |
3rd Quarter 2019 |
2nd Quarter 2021 |
Completed |
Clementi |
Repairs And Redecoration Works |
Blk 324,325, 332 to 342, 344, 353, 441A, 441B Clementi Ave 2/Ave 3/Ave 5 |
3rd Quarter 2019 |
3rd Quarter 2021 |
Completed |
Clementi |
Repairs And Redecoration Works |
Blk 416 to 425, 420A, 423A Clementi Ave 1 |
3rd Quarter 2019 |
1st Quarter 2021 |
Completed |
Jurong Central |
Repairs And Redecoration Works |
Blk 301 to 310, 371 to 374, 499 Jurong East St 32/St 41 |
3rd Quarter 2019 |
2nd Quarter 2021 |
Completed |
Jurong Central |
Repairs And Redecoration Works |
Blk 474 to 483 Jurong West St 41 |
3rd Quarter 2019 |
2nd Quarter 2021 |
Completed |
Taman Jurong |
Repairs And Redecoration Works |
Blk 345 to 355 Kang Ching Rd |
3rd Quarter 2019 |
3rd Quarter 2021 |
Completed |
Taman Jurong |
Repairs And Redecoration Works |
Blk 138A-D Yuan Ching Rd |
3rd Quarter 2019 |
2nd Quarter 2021 |
Completed |
Yuhua |
Repairs And Redecoration Works |
Blk 241 to 245 Jurong East St 24 |
3rd Quarter 2019 |
3rd Quarter 2021 |
Completed |
Bukit Batok |
Revitalisation Of Shops & Repairs and Redocoration Works |
Blk 150 to 159, 164 & 166 Bukit Batok St 11 / West Ave 8 |
4th Quarter 2018 |
3rd Quarter 2021 |
Completed |
Bukit Batok East |
Repairs And Redecoration Works |
Blk 285A-D, 286A-D, 287A-D, 288A-E Jurong East St 24 |
4th Quarter 2020 |
4th Quarter 2022 |
Completed |
Bukit Batok East |
Repairs And Redecoration Works |
Blk 265 to 284 Toh Guan Road |
4th Quarter 2020 |
3rd Quarter 2022 |
Completed |
Bukit Batok East |
Repairs And Redecoration Works |
Blk 201 to 208 Jurong East Street 21 |
4th Quarter 2021 |
4th Quarter 2022 |
In Progress |
Clementi |
Repairs And Redecoration Works |
Blk 442, 443, 446, 447,449,450,451 Clementi Ave 3 |
4th Quarter 2021 |
3rd Quarter 2022 |
In Progress |
Bukit Batok |
Repairs And Redecoration Works |
Blk 215 to 221,229, 230 Bukit Batok Street 21/Bukit Batok East Avenue 3 & Blk 228 Bukit Batok Central |
4th Quarter 2022 |
3rd Quarter 2023 |
In Progress |
Bukit Batok East |
Repairs And Redecoration Works |
Blk 288A to 288G & Blk 289A to 289G Bukit Batok Street 25 |
4th Quarter 2022 |
3rd Quarter 2023 |
In Progress |
Bukit Batok East |
Repairs And Redecoration Works |
Blk 254 to 265 Bukit Batok East Avenue 4 |
4th Quarter 2022 |
4th Quarter 2023 |
In Progress |
Clementi |
Repairs And Redecoration Works |
Blk 371 to 381 Clementi Avenue 4/5, Blk 349 to 352, BLK 354 TO 359, Blk 366 to 367 Clementi Avenue 2 & Blk 453 to 462 Clementi Avenue 3 |
4th Quarter 2022 |
1st Quarter 2024 |
In Progress |
Jurong Central |
Repairs And Redecoration Works |
Blk 311 to 316 Jurong East Street 32 & Blk 401 to 408 Jurong West Street 42 |
4th Quarter 2022 |
3rd Quarter 2023 |
In Progress |
Jurong Spring |
Repairs And Redecoration Works |
Blk 537 to 542 Jurong West Avenue 1 & Blk 515 to 520 Jurong West Street 52 |
4th Quarter 2022 |
4th Quarter 2023 |
In Progress |
Jurong Spring |
Repairs And Redecoration Works |
Blk 441 to 455 Jurong West Avenue 1/Jurong West Street 42 |
4th Quarter 2022 |
1st Quarter 2024 |
In Progress |
Jurong Spring |
Re-roofing Works |
Blk 441, 443, 444, 447 to 448 Jurong West Avenue 1/Jurong West Street 42 |
4th Quarter 2022 |
1st Quarter 2024 |
In Progress |
Yuhua |
Repairs And Redecoration Works |
Blk 108 to 116 Jurong East Street 13 & Blk 232 to 240 Jurong East Street 21 |
4th Quarter 2022 |
1st Quarter 2024 |
In Progress |